CONSTRUCTION DELAYS OF BUILDING REPAIR PROJECT AFTER THAILAND'S 2011 MAJOR FLOOD: CASE STUDY OF EDUCATIONAL GOVERNMENT SECTORS |
|---|---|
| รหัสดีโอไอ | |
| Creator | Chaisak Pisitpaibool |
| Title | CONSTRUCTION DELAYS OF BUILDING REPAIR PROJECT AFTER THAILAND'S 2011 MAJOR FLOOD: CASE STUDY OF EDUCATIONAL GOVERNMENT SECTORS |
| Contributor | Dhaninrat Suksomkullanan |
| Publisher | TUENGR Group |
| Publication Year | 2561 |
| Journal Title | International Transaction Journal of Engineering, Management, & Applied Sciences & Technologies |
| Journal Vol. | 9 |
| Journal No. | 4 |
| Page no. | 239-252 |
| Keyword | Repair delay, Building repair, Major flood, As-planned schedule, Construction delay, As-built schedule, Repair management |
| URL Website | http://tuengr.com |
| Website title | International Transaction Journal of Engineering, Management, & Applied Sciences & Technologies |
| ISSN | 2228-9860 |
| Abstract | Many buildings and properties of the central region of Thailand had been damaged by major flood in 2011. A set of nine buildings was selected as a case study to represent the building repair of the Higher Educational Government Sectors. Five approaches of the retrospective technique were used to analyze the impact of these delays on the schedule. The actual project completion was 17 days behind the as-plan schedule. However, time extensions obtained from schedule impact analysis techniques were -8, 0, 0, 17 and 29 days. Time extensions of 17 and 29 days were obtained from the approaches, which ignored all details of each delay. The negative time delays imply that the delay caused by the contractors had significant impacts on the repair project. Results from this study showed that the owner and excusable delay had no influence on request for extension because the longer delay durations of the System Work and the Other Jobs were caused by the contractor. The unexpected situation discovered was black molds growing on many pieces of gypsum board walls and ceilings, thus required replacements. |