Village Protection during Flooding by Wrap-Faced Embankment at Netrokona, Bangladesh |
---|---|
รหัสดีโอไอ | |
Creator | Ripon hore |
Title | Village Protection during Flooding by Wrap-Faced Embankment at Netrokona, Bangladesh |
Contributor | Mosharof Al Alim, Shoma Hore, Md. Saiful Islam, Abdul Siddik Hossain, Md. Mozammel Haque, Mehedi Ahmed Ansary |
Publisher | Southeast Asian Geotechnical Society |
Publication Year | 2568 |
Journal Title | Geotechnical Engineering Journal of SEAGS &AGSSEA |
Journal Vol. | N/A |
Journal No. | 1 |
Page no. | 1-8 |
Keyword | Wrap Face Embankment, Water Wave, Resilient, Jet Grouting |
URL Website | http://seags.ait.asia/ |
Website title | AGSSEA & SEAGS |
ISSN | 0046-5828 |
Abstract | In this paper, a case study is presented for a wrap-faced embankment. This type of embankment is found to be more efficient than a traditional embankment in case of stability and dynamic wave action under flooding. In the deltaic region, where soft soil exists below an embankment, it may suffer relatively more damage. Under this situation, a wrap-faced embankment may be a relatively better solution. The example presented here is based on a real-life wrap-faced embankment on a soft soil area located at Nowagoan Alga Hati village under Mohanganj upazila, Netrokona, Bangladesh. This study also discusses the application of soft soil improvement via jet grouting in some parts of the site. Jet grouting has improved soil stability and soil settling after being applied to the soil. Soil strength before and after jet grouting were 0.005 MPa and 0.94 MPa, respectively. The soil gains 186.8 times the strength of soil before applying jet grouting, which was very impressive. Jet grouting also improved the settlement of soil to a great extent. The areas without soil improvement by jet grouting showed more settlement than those with jet grouting. After flooding, the settlement of the wrap-faced embankment without jet grouting area was found to be 112 mm. On the other hand, settlement of wrap faced embankment (after flooding) in the jet grouting area was only 19 mm. This research output is significant for the design and implementation of the future flood-resilient embankment in the Deltaic region. |